Concrete scanning before core drilling: what to brief and what to check in the report
Published on by HR Utilities
Your mechanical contractor needs several new holes through an existing slab. You have a marked drawing and a date for the core driller, but the team has not agreed which areas the scanner should investigate or who will review the findings. Set those details before booking the scan. Give each proposed penetration an identifier, nominate a drawing revision and ask the scanner what access and information they need.
The aim is to give the people responsible for the work a clear account of the investigation. They need to connect each proposed hole or cut with the area the technician examined, the findings and any unanswered questions. A scanning report does not authorise drilling or cutting. The responsible project team must decide the work method and any further checks.
Send a brief tied to the proposed work
Ask the contractor to mark the proposed penetrations on a plan that the technician can use on site. Include the building, level and room or grid reference. Identify the concrete face from which the contractor intends to work. A photograph of a painted circle can help the technician recognise the location, but provide enough context for someone who has not visited the room.
Use a short penetration register alongside the drawing. Ask the relevant contractor or designer to supply the following details, rather than asking the scanner to infer the construction intent:
- The penetration ID and the current drawing revision, with proposed hole diameter or cut dimensions and the intended drilling or cutting direction.
- Available structural and services drawings, known previous alterations and the person who can answer questions about them.
- Access to the nominated faces, surface finishes or obstructions, and restrictions such as occupied areas or access times.
- The person who will receive the report, the format they need and the project review or permit steps they must complete.
Ask the technician to flag missing inputs before mobilisation. Keep changes to the register visible so the site supervisor and scanning team use the same scope.
Agree the scan area and access
Ask the technician to confirm the area they propose to investigate around each location and what access the chosen method needs. Let the competent practitioner define the investigation approach for the site. A generic distance around a painted mark cannot establish the required coverage for a particular slab and penetration.
Discuss surfaces that the technician cannot reach and areas the contractor cannot make available. Ask how the report will identify these exclusions. The supervisor should arrange agreed access or record the remaining limitation before the visit. Keep the scanner informed if another trade moves a proposed hole while preparing the area.
Ask how the technician will connect the surface marks to the report. Agree an identification method that the receiving team can follow, such as a location ID on a marked plan and corresponding photographs. This suggested record helps the reviewer confirm which proposed work the technician investigated.
Review the report against the penetration register
Start with the scope and location references. Check the report against the drawing revision that the contractor intends to use. Ask the technician to explain any difference before the team relies on the findings. For each nominated location, record the answer to these proposed review questions:
- Can the reviewer identify the examined area and connect it to the correct hole or cut?
- Does the technician distinguish detected features, interpretations and areas they could not resolve?
- Has the technician explained the method, relevant limitations and the basis of any depth estimates that the project team needs?
- Do the photographs, plan annotations and surface marks refer to the same location? Can the next trade understand the references?
- Does the report identify further information or investigation that the technician recommends before the work decision?
Ask for clarification of an unexplained blank area or ambiguous mark. Record who will answer the question and the work location affected. The project reviewer needs to understand the limitation; a general statement that scanning took place does not answer those questions.
Give the findings to the people responsible for the work
WorkSafe Victoria’s concrete cutting and drilling industry standard advises teams to confirm the location of structural components and services within the slab or wall. It calls for structural engineer advice for alterations and for advice and supervision when cutting structural components. Its services guidance also addresses drawings and confirmation of disconnections by the relevant service personnel. Read the current hosted document with the project’s safety arrangements.
Ask the site supervisor to route structural questions to the responsible engineer and services questions to the relevant competent personnel. Give them the drawing, investigation report and unresolved-location list together. Keep their instructions with the work record. The scanner supplies investigation findings within the agreed scope; the parties responsible for design, isolation and construction must make their respective decisions.
Recheck changes before the driller arrives
Compare the proposed work with the reviewed location register before handing it to the drilling contractor. A moved hole, changed diameter or different cutting direction may require the technician and responsible reviewer to reconsider the scope. Ask them what further investigation or review they need. Retain the superseded drawing so the next person can identify the change.
For an illustrative example, suppose a contractor relocates penetration P-04 after the scan because a duct conflicts with a ceiling support. The supervisor should identify the revised position and return it to the relevant reviewer and technician. The earlier report describes the original investigated location. Record the response to the revision before the contractor decides how to proceed.
Send HR Utilities the current penetration drawing, location register, available records and access details to discuss concrete scanning. Ask the team to confirm the investigation scope and reporting arrangements for your site. Contact HR Utilities with the project details before booking.
Sources
- WorkSafe Victoria: Safe concrete cutting and drilling industry standard Current hosted landing page identifies the concrete cutting and drilling guidance, its publication/review dates and hazard scope.
- WorkSafe Victoria: Safe concrete cutting and drilling industry standard PDF, sections 3.8 and 3.9 Confirm structural component/service locations; structural engineer advice for alterations and structural cuts; drawings and relevant service-person disconnection controls. Proposed briefing/register questions are editorial practice for review, not quoted regulatory requirements.